Nero fiddles, while the prospect of load shedding continues …

It appears the DoE, Nersa and Eskom have hardly grasped the depths of the power problem.
There have been suggestions that bureaucratic factions are deliberately trying to delay and frustrate the adoption of alternative small-scale power generation systems by individual electricity customers in order to protect their vested interests. Picture: Siphiwe Sibeko, Reuters

If Stage 2 load shedding in late 2018 and Stage 4 in February and March 2019 – 2 000 and 4 000 megawatts (MW) respectively – wasn’t enough, we face the looming prospect of further load shedding in the months ahead.

But there seems little sign that the bureaucrats at the Department of Energy (DoE), the National Energy Regulator of South Africa (Nersa), and Eskom have quite grasped the depth of the problem, or what is required to bring new generation capacity on stream quickly.

Eskom Generation week-on-week energy availability factor (EAF) for 2016, 2017, 2018 and to week 12 of 2019. (Source: Eskom; Graph: EE Publishers)

Having failed in the old Soviet Union, Cuba and Venezuela, South Africa still seems committed to a central command-and-control approach, particularly when it comes to electricity policy, planning, regulation and implementation – and it is proving way too slow and cumbersome for the needs of the modern economy.

If there is one thing the failed e-tolls project should have taught us it’s that, in the 4th Industrial Revolution, centrally imposed ‘solutions’ that are not seen by customers to have their interests and needs at heart will not work. Increasingly, customers have options and choices, including the option to ignore imposed solutions they perceive to be unworkable and dysfunctional.

Small-scale embedded generation in SA

Another example is now raising its ugly head. It comes in the form of the unworkable DoE, Nersa and Eskom policies, regulations, procedures and implementation of distributed small-scale embedded generation (SSEG) in South Africa.

SSEG comprises grid-tied and off-grid solar photovoltaic (PV) and other relatively small power generation systems, typically up to about 10MW, installed by customers ‘behind the meter’ on their premises. This is done for their own use, or to reduce grid electricity consumption costs, or even to supply electricity into the grid for use by others.

SSEG is generally applied in domestic, commercial, industrial and agricultural environments in homes, buildings, warehouses, parking lots, factories, mines and farms.

In times of rising electricity prices and utility supply constraints, SSEG provides benefits to the customer by reducing grid electricity usage costs and increasing security of supply, as well benefits to a constrained utility that is unable to meet electricity demand from its own centralised generation capacity and grid.

In metros such as Johannesburg, Ekurhuleni, Cape Town and others, the grid electrical energy and demand charges of existing electricity tariffs are already exceptionally high for commercial and industrial customers. For such customers, who use electricity mainly during the daylight working hours, the business case for solar PV SSEG is already a no-brainer, based on grid electricity cost savings alone.

Furthermore, SSEG has been identified as the quickest way to bring literally thousands of megawatts of new generation capacity to the grid within six months to a year, at no cost to the fiscus, Eskom or municipal electricity distributors, in order to relieve Eskom of the burden it is clearly failing to meet.

In light of these opportunities, the response by the DoE, Nersa and Eskom has been truly dismal.

Policy, regulatory and implementation chaos

On November 10 2017, a Licensing Exemption and Registration Notice for SSEG up to 1MW was published by the minister of energy in the form of Schedule 2 in the Electricity Regulation Act (ERA), to replace the previous Schedule 2 in the Act.

This new Schedule 2 exempted SSEG installations up to 1MW from the burdensome requirement of having to be licenced by Nersa, but instead requires grid-tied and off-grid SSEG installations up to 1MW to be registered with Nersa following a new registration process still to be put in place.

In addition, the new Schedule 2 requires all grid-tied and off-grid SSEG installations above 1MW, whether for own use or not, to have an allocation within the national Integrated Resource Plan for Electricity (IRP). If no allocation is provided in the IRP, then permission from the minister of energy to deviate from the IRP is required on a case-by-case basis. In addition, a full generation licence from the regulator, Nersa, is required for all SSEG installations above 1MW, following the same process as that required for a large Eskom power station of say 3 600MW.

But the madness continues. The notice of November 11 2017 contained several inconsistencies, misunderstandings and errors. Therefore on June 8 2018, the minister of energy published draft SSEG regulations (rules) and a notice of intention to amend the above Schedule 2 in the ERA, for public comment by July 8 2018. Despite the public comment process having taken place, to this day the flawed Schedule 2 of November 10 2017 has never been amended, and the SSEG regulations (rules) have never been published or gazetted.

Then in November 2018, the DoE provided Nersa with a new draft Licensing Exemption and Registration Notice and Schedule 2 for SSEG installations up to 1MW for concurrence by Nersa following a public process, before promulgation and gazetting. To date this has not been done.

Instead, on December 15 2018 Nersa issued a notice and commenced a public comment process over the festive season (closing January 15 2019) in respect of a proposed R200 registration fee for SSEG installations. Following from this, a R200 registration fee was decided upon by Nersa, but the R200 registration fee has never been gazetted, and the affected SSEG sector has never been advised.

Then in February 2019, the DoE provided Nersa with yet a further revised draft Licensing Exemption and Registration Notice and Schedule 2 for SSEG installations up to 1MW for concurrence by Nersa following a public process, before promulgation and gazetting. Again, to date this has still not been done.

However Nersa has advised EE Publishers that this second revised Notice and Schedule 2 is expected to go to the Nersa electricity sub-committee (ESC) and Nersa board for review in April 2019, after which there will likely be a 30-day public comment process, followed (hopefully) by concurrence by Nersa. The Notice and Schedule 2, once concurred by Nersa, will then go back to the DoE for review by the minister of energy, before final gazetting. No timeline has yet been provided.

Then in mid-March 2019, without advising the affected industry in any way, Nersa surreptitiously published the Registration Procedure for SSEG installations up to 1MW dated August 20 2018 on its website.

The registration procedure is however based on the flawed Schedule 2 of November 10 2017, which the minister of energy announced on June 8 2018 would be amended.

The regulations (rules) for SSEG installations that were published by the minister of energy on June 8 2018 for public comment have still not been gazetted, and no timeline has been provided for this.

Where things stand now

In the meantime, on March 27 2019 Nersa formally advised EE Publishers that, to date, Nersa has not accepted a single application for registration of an SSEG installation up to 100 kilowatts (kW). Instead Nersa has been advising prospective applicants to await the amended Schedule 2 of the ERA, as the requirements for registration may change.

Nersa has also advised EE Publishers that, to date, only 18 applications for registration of SSEG installations from 100kW to 1MW have been received, while one has been rejected, and the remaining 17 are still being processed. The applications would then need to be approved by the Nersa ESC and board before registration can take place.

Thus, to date, not a single SSEG installation up to 1MW has been registered by Nersa since the Licensing Exemption and Registration Notice for SSEG up to 1MW was published by the minister of energy on November 11 2017.

As indicated earlier, SSEG installations above 1MW require authorisation by the minister of energy for deviation from the IRP, as there is no allocation in the current IRP 2010-2030 for SSEG above 1MW. For about a year now, DoE officials have been advising prospective applicants for SSEG installations above 1MW to await the new IRP, which may include an allocation for SSEG installations above 1MW.

The latest draft IRP 2019 has only recently been received by Nedlac, and is currently undergoing a Nedlac consultation process between government, business, labour and communities. Only thereafter can the draft IRP 2019 proceed to the cabinet for policy intervention, before final approval and gazetting. Nedlac has advised EE Publishers that its process typically takes between three and six months.

Power to some customers

Incumbent monopoly electricity utilities and electricity distributors perceive that the widespread adoption of SSEG undermines their revenue and business case. As well-heeled domestic, commercial, industrial and agricultural customers install SSEG to protect their interests, they argue that poorer customers will face rising prices as utilities increase their tariffs to cover their declining sales volumes in terms of the current regulatory pricing dispensation.

Some customers see the chaotic policy, legal, regulatory and implementation framework for SSEG in South Africa as perhaps just another symptom of incompetence by and mismanagement between the various sate entities. Others suggest that factions within the DoE, Nersa and Eskom are deliberately trying to delay and frustrate the adoption of SSEG as a part of their political agendas to protect vested interests in the status quo.

It should be noted that, in theory, an SSEG installation up to 1MW cannot be legally connected to the distribution grid or operated unless it has been registered with Nersa. Similarly, in theory, SSEG installations above 1MW cannot be legally connected to the distribution grid or operated without written permission to deviate from the IRP from the minister of energy and a generation licence from Nersa.

The reality, of course, is that in face of cumbersome and dysfunctional SSEG policies, regulations and procedures, the legal requirements of the central planners and regulator are simply ignored as customers do their own thing, knowing that the regulations are essentially unenforceable.

However one thing is certain: SSEG provides the quickest option at least cost to government and Eskom for new generation capacity in South Africa. By lifting the policy and regulatory hurdles, and through active encouragement and incentivisation, SSEG could deliver several thousand megawatts of new generation capacity within six months to one year that would avoid Stage 4 load shedding of the productive economy during daylight working hours.

Chris Yelland is investigative editor at EE Publishers

COMMENTS   10

Sort by:
  • Oldest first
  • Newest first
  • Top voted

You must be signed in to comment.

SIGN IN SIGN UP

I for one will do a e toll ignore on anyone that wants to regulate my solar system !!!!

DA aka ANC-Lite has already started with this in Cape Town…

“However one thing is certain: SSEG provides the quickest option at least cost to government and Eskom for new generation capacity in South Africa.”

Eskom and government see it as the highest cost option… less electricity tariff revenue to squander.

Is Mr Gordhan really capable of managing this mess? After all he was the Zupta CFO for years….

If you monopolize a critical area such as electricity, there is an implicit promise to be able to meet the total demand. If you fail at that it feels to me as if there should be some legal or constitutional basis to challenge that monopoly position. Surely it cannot be that you legislate for a monopoly and then fail to provide that service.

NERSA is a worthless burocracy which only serves the purpose of employing cadres.

The socialist nirvana is upon us. Blundering bureaucrats, drawing huge salaries, stumble from one self-created clusterf# to the next. Congratulatory back-slaps and Johnny Blue all around.
We need a Nuremberg trial for these people.

AT Chis Yelland
Interesting to see eskom in Atlantis?ankerlig are building 2 additional diesel storage tanks, (visible form public road side in case of conspiracy theorists ask)…
IMO this imply :
– Additional storage of diesel because ankerlig will run more than then mentioned 2 hours peak demand support
– More expensive electricity
– Paradoxically it imply, if eskom waste more we pay more

So are the plans really to get the other stations more dependable or to pull the wool over our eye’s

I wish upon SA an abundance of SUN,
in the years to come!!

(Despite the hidden message, it even rhymes *lol*)

Some customers see the chaotic policy, legal, regulatory and implementation framework for SSEG in South Africa as perhaps just another symptom of incompetence by and mismanagement between the various state entities. Others suggest that factions within the DoE, Nersa and Eskom are deliberately trying to delay and frustrate the adoption of SSEG as a part of their political agendas to protect vested interests in the status quo.

I have absolutely no doubt that it’s a combination of the above! One thing we can NEVER expect from the ANC is competent, sensible legislation that puts the needs of South Africans first.

End of comments.

LATEST CURRENCIES  

USD / ZAR
GBP / ZAR
EUR / ZAR
BTC / USD

Podcasts

INSIDER SUBSCRIPTIONS APP VIDEOS RADIO / LISTEN LIVE SHOP OFFERS WEBINARS NEWSLETTERS TRENDING PORTFOLIO TOOL CPD HUB

Follow us:

Search Articles:
Click a Company: