AA urges Gauteng government to reject Gautrain extension plans

Says the creation of a provincial-scale bus system instead will be the ‘most appropriate solution to mass transit’ in SA’s economic hub.
The 'Gautrain 2' expansion proposes another 150km of high-speed rail and a further 19 stations in key nodes. Image: Moneyweb

The Automobile Association (AA) has called on the Gauteng Provincial Government to reject proposed route extensions to the Gautrain rapid rail network as it will perpetuate a system that caters for the minority of citizens in the province instead of the mass market.

In a detailed submission, the AA also highlighted several factors it believes negate the extension of Gautrain, including the fact that the current demand on the system is low and economic viability cannot be established within reasonable risk parameters.

Read:

Gautrain: Purchase of more rolling stock put on hold

M&R receives R285m Gautrain business disruption insurance payout

However, the Gautrain Management Agency (GMA) stressed that the route of the proposed extensions to the Gautrain network has not yet been finalised.

The GMA said the route determination process that is currently underway is legislated through Section 6 of the Gauteng Transport Infrastructure Act (GTIA), which is the first step in the process of defining the rail reserve for the future railway line for the Gautrain Rapid Rail Integrated Network (GRRIN) project.

It said the purpose of this process is to identify the best possible route, which, when determined, results in a strip of 200 metres on either side of the proposed alignment that will be protected by the Gauteng Province.

The GMA said it responds to all of the comments it receives and these comments and responses are collated into a report that, together with the proposed route alignment documentation, is presented to the MEC for Public Transport and Roads Infrastructure (MEC) for consideration as part of the process to determine the final route.

Next step

“The next step in the process is to undertake the preliminary design of the proposed railway system and include a full Environmental Impact Assessment (EIA).

“This is also a legal requirement in terms of the GTIA and entails further consultation with all interested and affected parties,” it said.

The current Gautrain network comprises 80km of rail along two route links: a link between Tshwane and Johannesburg and a link between OR Tambo International Airport and Sandton.

Gautrain 2 proposes building another 150km of rail and a further 19 stations, with the proposed first phase comprising a new line from Marlboro through Sandton and Randburg to Cosmo City and then to Little Falls.

Lanseria is the ultimate destination for a proposed rail service running east-west between the two airports in a later proposed phase.

Read:

Gautrain 2 can only realistically start at the end of 2024

Lanseria International eyes ‘airport city’ development

The second phase of the proposed expansion will extend the line from Little Falls through Roodepoort to Jabulani in northern Soweto.

Three more proposed phases are envisaged to complete the network.

Funding

The GMA has been engaging with National Treasury about the proposed Gautrain expansion project, including other sources of funding for the proposed project and the need to move people off the roads and away from carbon-intensive modes of transport.

It emerged during a virtual panel discussion in September 2020 that motorists and taxpayers were set to become the cash cow to enable the government to reduce its percentage of the funding of the multi-billion rand proposed expansion of the Gautrain.

GMA CEO William Dachs said: “We firmly believe the people in cars don’t pay their fair share in terms of the taxes that they pay and the failure of the e-tolls system has perpetuated that problem.”

The AA said the Gautrain does not carry enough passengers currently and spending valuable financial resources now to continue with a system that does not have a demand, at the expense of better, more efficient, and more affordable transport does not make any sense.

“We are in favour of alternatives that provide solutions to vehicle usage and which reduce pollution and congestion, but the Gautrain is not that solution,” it said.

Read: Motorists set to pay for Gautrain expansion

The AA added that low usage of the Gautrain put additional pressure on the province’s transport budget, which effectively means other transport options are not properly funded and again disadvantages the mass market, which needs it most.

Patronage guarantee ‘disgraceful and outrageous’

The AA is also critical of the patronage guarantee, a subsidy to the Bombela Concession Company (BCC), which operates the Gautrain, when its total revenue is below a contractually agreed amount.

It said the patronage guarantee is “a disgraceful and outrageous agreement which has cost taxpayers almost R12 billion since 2012 just because not enough people see value in using the Gautrain”.

The AA urged the Gauteng Provincial Government to invest heavily in the creation of a provincial-scale bus system as the most appropriate solution to mass transit in Gauteng.

“The provision of safe cycle lanes and solutions for those who walk the ‘last mile’ to work and home must also be considered. This has inexpensive infrastructure requirements and will integrate with all other modes of transport.

“It will also encourage non-motorised transport and bring cost-effective travel within reach of all citizens,” it said.

The AA said instead of solving the province’s dire transport crisis, the Gautrain has become “a system for the well-off who in any event have access to other modes of transport”.

“To extend the Gautrain services now is economically inappropriate and unacceptable, and the process should be halted immediately,” it said.

‘Big mistake’

The Competition Commission said in February 2019 when it released its preliminary report into its market inquiry into land based public passenger transport that it believed the Gautrain was a big policy mistake.

It recommended that  the Gauteng provincial government take over Metrorail and integrate it with the Gautrain to run “a single system that doesn’t separate people according to class”.

Read: Gautrain a big policy mistake – CompCom

The GMA said the Gauteng provincial government in 2013 completed a 25-year Gauteng Integrated Transport Master Plan (GITMP25), which included transport modelling that predicted a significant increase in traffic congestion, travel times, and associated challenges including greenhouse emissions from 2025.

It said the outcome of this affirmed, among other things, that the passenger rail network should form the backbone of a modernised and integrated transport system in the province.

The GMA said the Gauteng MEC for Roads and Transport in 2014 commissioned the agency to develop a comprehensive strategy to improve mobility in Gauteng, which entailed conducting a comprehensive feasibility study to investigate possible extensions to the Gautrain.

‘Significant benefits’

It said this feasibility study, completed in 2016, concluded that the Gautrain extensions will provide significant economic and transport-related benefits.

These included transformational impact on the Gauteng economy; the modernisation of public transport; greener transportation solutions for a healthier community; passenger access and mobility; improved spatial development; environmental impact; increase in local content; business development; and the creation of jobs and poverty alleviation.

The GMA said this feasibility study is currently subject to the National Treasury approval process, which will enable the commencement of the procurement for Phase 1 of the extensions project.

“The GRRIN extensions will therefore form part of a modernised and integrated transport system that enables sustainable mobility in the future and thus are part of the entire public transport system in Gauteng and not only the Gautrain service,” it said.

Please consider contributing as little as R20 in appreciation of our quality independent financial journalism.

AUTHOR PROFILE

COMMENTS   10

Sort by:
  • Oldest first
  • Newest first
  • Top voted

You must be signed in to comment.

SIGN IN SIGN UP

Say what?! I love the Gautrain. Why would the be against 1st class transportation? Would the AA rather have the taxi mafia shooting it out with bus services?

Actually it would be great if the Gautrain could run at 240 and all the way to Durban (with a few quick stops at places like Harrismith and PMB).

“caters for the minority of citizens in the province instead of the mass market.”

SA is the most unequal society according to gini index. This is a fact AA needs to embrace. I don’t see AA opening membership and other perks to taxi’s and government vehicles.

You pay for the service one receives. If the government offered this world class service to other spheres of public service; there would be no need to private hospitals and schools.

Ah but it should make a profit and not be subsidised by rate and taxpayers.

It is patently obvious that the brains of the central and local governments are that of a neut

The bigger the project the bigger the feeding trough. One simply has to look at the two feeding troughs commonly know as Medupi and Khusili. Looting simply outweighs practicality, sensibility, the will of the people and the betterment of services and the country in general.

Buses must be integrated with the Gautrain. But on the same token, do you want the taxis to go crazy again?

You have to bride the taxis for the buses when you can avoid the roads all together with the Gautrain. I am all for the Gautrain expansion, especially Fourways to Sandton and Lanseria

What the hell!!!

“GMA CEO William Dachs said: “We firmly believe the people in cars don’t pay their fair share in terms of the taxes that they pay and the failure of the e-tolls system has perpetuated that problem.”

Who is this guy spewing this kind of false rhetoric?? Just look at the tax structure of petrol and diesel to see how much tax motorists pay on every litre of fuel.

Agreed, I nearly went keyboard warrior when I saw that statement.

The largest inefficiency we have is government’s inability to spend tax payer money effectively, which creates environment catastrophes such as raw sewage running into our rivers and building more coal fire power stations.

Examples can be seen at ESKOM who have spent twice the budget to build the new power stations over a 15 year period, this is something that most other countries only take 5 years to do.

Trains work better than buses but do we really need the very expensive fast train system? Speed only matters over distances. Gautrain distances between stations is so small that the train has hardly reached cruising speed before it slows down again.

80km/h is plenty fast enough for some of the largest metro transport systems in the world (NY, London, Atlanta, Paris, etc)

“We are in favour of alternatives that provide solutions to vehicle usage and which reduce pollution and congestion, but the Gautrain is not that solution, it said.” – okay so then what is the solution? Adding busses to an already congested road network, along with taxi operators who will make your brilliant idea unworkable?
Clever AA, very clever…

End of comments.

LATEST CURRENCIES  

USD / ZAR
GBP / ZAR
EUR / ZAR
BTC / USD

Podcasts

INSIDER SUBSCRIPTIONS APP VIDEOS RADIO / LISTEN LIVE SHOP OFFERS WEBINARS NEWSLETTERS TRENDING PORTFOLIO TOOL CPD HUB

Follow us:

Search Articles:
Click a Company: