Cost of new power generation in South Africa

CSIR study shows significant reduction in the cost of energy from wind and solar PV generation technologies.

The Energy Centre of the CSIR has moved to provide updated and consistent information on the cost of new power from wind, solar PV, baseload coal IPP, baseload Eskom coal, and nuclear power generation technologies in South Africa.

In a presentation dated October 14 2014, the head of CSIR’s Energy Centre, Dr Tobias Bischof-Niemz, and Ruan Fourie, energy economist at CSIR’s Energy Centre, provide a comparative analysis for new power in South Africa based on recent coal IPP bid price announcements by Minister of Energy Tina Joemat-Pettersson on October 10 2016, and other data.

This study is seen as important for any review of the draft update to the Integrated Resource Plan for Electricity (Draft IRP) currently in progress by the Department of Energy (DoE).

The Draft IRP was to have been presented to the cabinet last week, and thereafter made available to the public for comment, but this has since been delayed, with no further dates being given.

Since the previous due date of end March 2016, the request for proposals (RFP) for the proposed 9.6GW new-nuclear build in South Africa has also been further delayed from the revised issue date of end September 2016.

However, it is known that in the meantime various stakeholder structures reporting to the minister of energy are currently reviewing the Draft IRP and its proposals for new renewable, baseload coal and nuclear power, and making further input and recommendations.

The CSIR study shows the significant reduction in the cost of energy from wind and solar PV generation technologies in South Africa since submission of bids for Window 1 of the renewable energy IPP programme  (REIPPP) on November 4 2011, to those of the expedited round of Window 4 on November 4 2015.

 

 re-pic-1

Source: CSIR presentation, 14 October 2016

The result of this reduction is that new power from solar PV and wind today is at least 40% cheaper than that from new baseload coal today.

Recent bid prices for solar PV in Mexico at R0.49/kWh, Dubai at R0.42/kWh, Chile at R0.41/kWh and Abu Dhabi at R0.34/kWh (all based on US $1.00 = R14.00) have shown that this significantly reducing price trend is continuing still further globally.

The solar PV, wind and coal IPP tariffs presented by the CSIR for South Africa are fully comparable, because they are all based on long-term take-or-pay contracts with the same off-taker (Eskom). The tariffs have also been suitably adjusted for consistency.

In this regard, the price of R0,61/kWh for new wind and solar PV, and R1.03/kWh for new coal IPPs, reflects an adjustment of the bid prices to ensure a common base-date of April 2016, a consistent present-value-equivalent escalation index of CPI+1%-point, and exclusion of the carbon tax of R120/t of CO2 emitted from the coal IPP tariff.

The CSIR study also presents the latest updated levelised cost of electricity (LCOE) calculations for new Eskom baseload coal at R1.10 to R1.20/kWh, new baseload nuclear at R1.20 to R1.30/kWh, new mid-merit gas (CCGT) at R1.00 to R1.20/kWh, and new mid-merit coal at R1.50/kWh.

 

re-pic-2

 

Source: CSIR presentation, 14 October 2016

The CSIR study and presentation confirms EE Publisher’s earlier LCOE calculations for the cost of for new nuclear power in South Africa. The EE Publishers study calculated an LCOE of R1.30/kWh for nuclear power based on Rosatom VVER 1 200 reactors, and provided a detailed sensitivity analysis for the various assumptions used.

The CSIR study and presentation of the LCOE for new Eskom baseload coal power is also in line with EE Publishers’ own LCOE calculation for Eskom’s new Medupi and Kusile baseload coal-fired power stations of R1.05/kWh and R1.16/kWh respectively.

After first rubbishing EE Publishers’ LCOE calculations for Medupi and Kusile, citing its own calculation of R0.71/kWh and R0.82/kWh for Medupi and Kusile respectively, Eskom’s head of generation, Matshela Koko, subsequently undertook to have Eskom’s and EE Publishers LCOE calculations independently reviewed.

However, after receiving EE Publishers’ detailed analysis of the differences between Eskom’s and EE Publishers’ methodology and assumptions, Eskom has since reneged on this undertaking, and ignored all efforts to proceed with the independent review it had proposed.

Chris Yelland is investigative editor at EE Publishers

COMMENTS   5

Sort by:
  • Oldest first
  • Newest first
  • Top voted

You must be signed in to comment.

SIGN IN SIGN UP

In trying to justify the cost of nuclear power, our sneaky energy minister made a comment to parliament that renewables would also cost the country more than a trillion Rand.

This is highly misleading statement and nobody seems to have called her to order. The private sector is funding the capital cost of renewables so she can only be referring to the electricity tariff here. Using the ministers logic would mean that we must then add the required electricity tariff to nuclear and that would take the “cost” as per the ministers definition to around R3 trillion for nuclear.

I think I did read somewhere that, overall, renewable were costing Eskom and average of something like R2,03/kWh. But this may well be due to BEE/ANC “looting”, outdated technology originally etc. Maybe EE or Chris could comment?

Could be, but that is largely Eskom’s fault for delaying more recent projects where the cost is so much lower, per the CSIR graph above. If you bring those projects online then the average cost would decline significantly. Might be the skeptic in me but perhaps these low cost options are threatening Eskom’s ability to effectively build generation (given recent experiences).

You see, when you “decolonise” the free market, you are left with Eskom. The SOE’s are a dumping yard for all useless ANC cadres. This is what “africanization” of institutions look like.

Re more nuclear power stations:we can’t afford them,they’ll bankrupt SA, they’ll make us economic slaves to the IMF/World bank,China or Russia.And all because Eskom will not acknowledge that power generation is changing to stand-alone house generation and the ongoing revolution in renewables is going to make dinosaurs – like Eskom – redundant.

End of comments.

LATEST CURRENCIES  

USD / ZAR
GBP / ZAR
EUR / ZAR

Podcasts

INSIDER SUBSCRIPTIONS APP VIDEOS RADIO / PODCASTS SHOP OFFERS WEBINARS NEWSLETTERS TRENDING PORTFOLIO TOOL CPD HUB

Follow us:

Search Articles:Advanced Search
Click a Company: