Eskom cancels Alstom’s R1bn Kusile contract and reinstates ABB.

On March 20 2014, Eskom announced the termination, with effect from April 17 2015, of the approximately R1 billion control and instrumentation (C&I) works contract placed with Alstom in 2011 for its 4800 MW Kusile power station, which is currently under construction near eMalahleni (Witbank) in Mpumalanga.

Shortly thereafter Eskom announced that it had appointed ABB South Africa to execute the C&I contract at Kusile. The ABB contract is valued at approximately R1.5 billion, and it is understood that ABB will essentially be starting the C&I Works at Kusile from scratch.

In addition to payment for work already completed, Eskom had to pay a cancellation fee of some R40 million to Alstom to achieve a consensual termination agreement on a “co-operative walk-away basis”. The cancellation has delayed the Kusile project by about a year.

Alstom will continue with the C&I Works contract at Eskom’s 4800 MW Medupi site near Lephalale in Limpopo, excluding the boiler protection system on Units 5 and 6 which was removed from Alstom’s scope and given to Siemens in 2014.

A preliminary engineering and design process in anticipation of a possible cancellation of the Alstom C&I contract was conducted by Eskom with both ABB and Siemens during the previous year, and both ABB and Siemens subsequently submitted tenders for the new C&I contract.

It is understood that while ABB’s tender was some 25% higher than that of Siemens, ABB offered a six-week shorter completion programme for Unit 1 and the ‘balance of plant’, which ABB is committed to complete by February 2016. Siemens could only commit to April 2016 for this critical stage.

Two independent sources have since indicated that Siemens is considering seeking a court interdict to stop Eskom placing the Kusile C&I contract with ABB.

The Eskom’s acting executive for group capital, Abram Masango welcomed the new contract saying: “We believe that the procurement process that we followed will ensure a seamless transition and that it formed a strong basis for a competent supplier to deliver a quality product within agreed timelines”.

ABB is supplying the control and instrumentation system for the entire Kusile plant, including boiler protection and plant simulator, engineering, installation, commissioning, optimisation and training.

ABB South Africa CEO Leon Viljoen says that local software engineering by experienced and qualified local ABB engineers bodes well for South Africa and Eskom. He adds that “ABB is comfortable with its programme to completion for the C&I works at Kusile site, and in view of the political sensitivity of the project, ABB is being careful not to over-promise and under-deliver”.

With six 800 MW super-critical generation units, Kusile will be the fourth largest coal-fired power station in the world and the largest dry-cooled power station in the southern hemisphere. Kusile will be the first coal-fired power station in Africa to use wet flue gas desulphurisation technology in its plant boilers.

Originally scheduled to have all six units fully operational and delivering commercial power into the grid by the end of 2014, the project is running six years late, with massive cost overruns at least twice that originally approved. At present the commercial operation date of the last unit (Unit 6) at Kusile is only scheduled for the end of 2020 at the earliest.

Chris Yelland is the investigative editor at EE Publishers

VIDEOS

COMMENTS   4

Sort by:
  • Oldest first
  • Newest first
  • Top voted

You must be signed in and an Insider Gold subscriber to comment.

SUBSCRIBE NOW SIGN IN

I wonder how much bribery went on for ABB to aquire the contract. whith all this wheeling and dealing no wonder the project is 6 years behind, the chances are there is more money to be wasted and the date will probably be moved anouther 2 years!

Another fine example of why the “user pay” principle will not work in corrupt SA. They do not care about loading the price because the “user” will just have to pay more. Ask Scamral

ABB were probably offering a bigger bribe.

Commenters are mentioning bribes, I am not certain. Alstom was responsible for the trains of the last metro line in Budapest and even that was delayed because Alstom did not manage to finish deliver on time.

End of comments.

LATEST CURRENCIES  

USD / ZAR
GBP / ZAR
EUR / ZAR
BTC / USD

Podcasts

INSIDER SUBSCRIPTION APP VIDEOS RADIO / LISTEN LIVE SHOP OFFERS WEBINARS NEWSLETTERS TRENDING

Follow us:

Search Articles:
Click a Company: