Intervene now, or load shedding could increase ten-fold

Meridian Economics looks at SA’s mistakes and the solutions that could eliminate load shedding by 2024.
Image: Moneyweb

Load shedding can be stopped by 2024, but that will require strong leadership from the presidency to see that extraordinary interventions on many fronts are implemented without any delay, says think tank Meridian Economics.

This includes lifting the licensing exemption for generation plants from 100MW to 1000MW.

It says that without any intervention load shedding will likely increase up to four-fold in 2023, compared with 2021, up to five-fold in 2024 and up to ten-fold in 2026.

Meridian Economics’s suggested solution includes a drastic escalation of wind and solar energy, changes in the tariff regime to incentivise owners of distributed generation to push excess energy into the grid, and the removal of stumbling blocks in current government procurement from independent power producers (IPPs).

Meridian, led by respected energy expert Dr Grove Steyn, is releasing two reports (‘Resolving The Power Crisis’) that explains its research and proposals on Monday, June 13.

Read:
Part A: Insights from 2021 – SA’s worst load shedding year so far
Part B: An achievable game plan to end load shedding

Go-slow consequences

In the first report, the think tank investigated what the load shedding picture would have looked like if government’s procurement of renewable energy from IPPs continued without the interruption that came after Eskom refused to sign power purchase agreements in 2016.

They were eventually signed in 2018, but the procurement programme only recently restarted at a slow pace.

Meridian found that, if the system operator had access to 5 000 MW (equal to about two bid rounds) of additional wind and solar energy in 2021, it would not only have prevented the worst year of load shedding ever – it would have eliminated 96.5% of load shedding that year.

Source: Meridian Economics

Combined with “a modest expansion” of Eskom’s programme to buy power back from industrial customers, demand management as well as 2 000 MW of one-hour batteries, load shedding could have been completely eliminated.

That would have come at no cost to Eskom. The utility would in fact have saved R2.5 billion due to more economical use of its coal-fired power station, open-cycle gas turbines and pump-storage plants, Meridian found.

Power proposals

In the second paper Meridian identifies problems in the current steps aimed at alleviating the electricity crisis. It develops a solution and adjusts it to mitigate against several execution risks and then develops an ambitious game plan to eliminate load shedding by 2024.

The paper also sets out the assumptions regarding demand growth and other crucial variables.

According to Meridian, it is unlikely that the decline in the availability of Eskom’s power stations will be contained to less that 2% per annum while the pressure on the system leaves the utility with little space to do proper maintenance. It further expects demand to grow to pre-Covid levels.

The think tank points out that government’s 1 850 MW emergency power purchase programme (RMIPPPP) and the fifth renewable energy bid round (BW5) featured aggressive pricing that was calculated before the Covid-19 pandemic resulted in supply chain disruptions and huge price increases.

This, together with unrealistic and impractical requirements for local content relating largely to solar panels and bad procurement design, will lead to many of these projects failing, according to Meridian.

It proposes the following urgent measures as a game plan to eliminate load shedding by 2024 and ensure energy security by 2025:

  1. Eliminate or drastically reduce local content requirements on PV modules;
  2. Fix RMIPPPP design flaws to enable all the projects with PV, wind and storage to proceed and the entire project energy and capacity to be made available to the system;
  3. Implement across the board price increases for BW5 projects to compensate for large cost escalations to ensure viability;
  4. Accelerate uptake in the distributed generation market by implementing further licence exemptions up to 1 000 MW and net feed-in tariffs and further tax incentives;
  5. Expand REIPPPP (Renewable Energy IPP Procurement Programme) BW6 to double its current size and launch it in time with stronger incentives for early energy;
  6. Expedite the procurement of additional peaking capacity, demand response capacity and storage;
  7. Implement Eskom’s Just Energy Transition (JET) renewable energy public-private partnership (PPP) projects;
  8. Clarify and unlock the opportunity for municipalities to rapidly procure new capacity;
  9. Bolster the Eskom grid connection process;
  10. Fix and establish key institutions, including ironing out issues in the IPP Office and energy regulator Nersa;
  11. Expedite additional amendments to Schedule 2 of the Energy Regulation Act and issue new ministerial announcements/determinations;
  12. Establish a dedicated well-resourced power crisis implementation unit inside the presidency to drive and monitor the implementation of these measures.

 

Source: Meridian Economics

COMMENTS   4

Sort by:
  • Oldest first
  • Newest first
  • Top voted

You must be signed in and an Insider Gold subscriber to comment.

SUBSCRIBE NOW SIGN IN

Feel free to read my comments below the article:
https://www.moneyweb.co.za/news/south-africa/never-mind-winter-load-shedding-is-likely-to-get-much-worse-from-september/
For the ones not being a MW insider :
“Indeed these REIPP projects are moving at a pace of a 95 year old snail, with Parkinson and long COVID.
CR should never be allowed a second term as Prez of SA, we need a complete regime change come 2024 elections.
We need at least two BWs of 5 GW each yearly to get anywhere. And the whole bureaucratic process should be immensely be simplified and not take more than 6 months, for permits, FC, EIA and all the rest.
All requirements for BEE, community projects and local content should be scrapped ASAP. Size should not be limited to 75 for PV, and 140 MW for wind. There should also be room for projects which include BESS, and CSP+TS, Concentrated Solar Power with Thermal Storage. Power produced during peak hrs should be priced higher. Eskom has to immensely hurry up spending R 100 B at least in extending the grid, especially to the NC. Maybe the R 40 B that will be spent on FGD at Kusile, is better used for improving the transmission system. Many countries intend to close coal fired power generation by 2030, SA should close even Kusile and Medupi not later than 2035.”
In November last year I took part in a webinar discussing the outcome of the preferred bidders for BW 6. The first one after the facilitator to give a lengthy presentation was the head of the IPP office Bernard Magoro. He spent most of his time on elaborating on the BEE scorecard. Pathetic actually.
I made a written question to the webinar : why not scrap all BBBEE, community participation and local content requirements ? Must have been regarded as possibly too direct, and not PC.

Sorry, the Webinar in November was about BW 5.

Only 2 problems — The ANC will do nothing and Loadshedding will become the norm – ala the DRC.

We have already signed a deal for solar plus storage that delivers power 16h a day. The ratio for that is basically 3.5MW solar plus 7h storage delivers 1MW constant 16h a day 365 days a year. No intermittency – it is a UPS class service. That price was R1.88/kWh.

The ratios would change but if instead of 5AM to 9PM (the 16h a day window in this deal) the requirement focus was more power 6AM to 9AM and 6PM to 9PM, that would yield power in the windows when we are running diesel at about three times the cost of solar plus storage.

Somebody can run the math but likely 3.5GW solar power and 10h or so battery storage would yield 500MW for 16h a day and 1.5GW for 6h a day in the crunch times. Almost exactly a stage less loadshed and a heck of a lot of diesel that presently tries to avoid loadshed avoided.

That could be deployed well before the end of 2023.

We declared a state of emergency for covid that said we can’t buy T shirts or walk on the beach. This is a REAL emergency

End of comments.

LATEST CURRENCIES  

USD / ZAR
GBP / ZAR
EUR / ZAR
BTC / USD

Subscribe to our mailing list

* indicates required
Moneyweb newsletters

Instrument Details  

You do not have any portfolios, please create one here.
You do not have an alert portfolio, please create one here.
INSIDER SUBSCRIPTION APP VIDEOS RADIO / LISTEN LIVE SHOP OFFERS WEBINARS NEWSLETTERS TRENDING

Follow us:

Search Articles:
Click a Company: