South African activists sued the nation’s energy regulator over its award of generation licences to Karpowership, threatening to further delay a programme to add power to the grid to alleviate recurrent outages.
Read:
Floating powerships expand globally as South African plans stall
SA’s $6.5bn in power plans delayed again
The National Energy Regulator of South Africa (Nersa) granted the permits to the Turkish company in September, allowing it to supply the country from three ship-mounted power plants. Progress has been stalled by another court case over the award of the contracts and Karpowership has yet to secure environmental approval or the right to moor its vessel in the country’s ports.
“The law requires that Nersa acts in the best interests of the country, but the Organisation Undoing Tax Abuse (Outa) believes that Nersa has failed to do so,” the Johannesburg-based group said in a statement on Thursday, citing concerns over a number of matters including the price of the Karpowership contracts and its impact on the climate.
The award of the contracts to allow Karpowership to supply South Africa with 1 220 megawatts of electricity from gas-fired power plants are part of an emergency programme to procure 2 000 megawatts of power. The country has suffered intermittent power outages for more than a decade.
Read:
Eskom seeks indemnity from Karpowership in power-purchase pact
Renewable procurement picks up steam with opening of new bid window
The case was filed in the Pretoria High Court on April 26.