South Africa’s efforts to tackle its energy crisis lack urgency and coherence

South Africa’s electricity infrastructure has been degrading in the past decade, with both scheduled and unscheduled power outages on the increase.
South Africa’s energy sector is being guided by an outdated Integrated Resource Plan. Charles HB Mercer via Shutterstock

South Africa’s electricity infrastructure has been degrading in the past decade, with both scheduled and unscheduled power outages on the increase. Despite slowed economic activity due to the COVID-19 pandemic, the country experienced 1130 hours of planned power cuts in 2021, the highest ever.

This not only leads to anger and frustration among the public, but also clearly handicaps businesses and their productivity. The alleviation of the electricity crisis is therefore a critical precondition for the country’s economic recovery. This is why observers have been watching the President Cyril Ramaphosa’s strategy and its implementation with much anticipation.

In the 2021 State of the Nation Address Ramaphosa listed “the rapid expansion of our energy generation capacity” as one of government’s five top priorities. This year he reiterated that this had not changed. This would clearly be a major deliverable on which his government’s success would be judged on.

In his 2022 State of the Nation Address he didn’t touch on an issue that would have raised confidence that his government is making progress on energy. He didn’t give any indications of plans to review the Integrated Resource Plan. The last Integrated Resource Plan was adopted in 2019. The plan, which guides power station development and associated timelines, should be reviewed every two years.

A revised plan is needed, especially in view of the rapid developments in energy generating technologies. The 2019 plan is effectively already obsolete, and updated projections are likely to lead to substantially changed optimal electricity generating scenarios.

Construction delays

The 2019 Integrated Resource Plan made provision for immediate action to construct 1600 MW of wind power, 1000 MW of solar power and 513 MW of electricity storage capacity to bring on line by 2022. But these are only expected to be ready in early 2024. Projects due to be completed in 2023 include another 2600 MW of wind and solar and 750 MW of new coal, but the process to identify the sites and developers hasn’t started. This means that all these initiatives are two years behind schedule.

The coal project is facing severe head winds as a consequence of changed perceptions of coal due to its role in global warming. But there’s no excuse for the delays in initiating the officially endorsed plan to develop the renewable energy plants.

The Minerals and Energy Minister Gwede Mantashe, the implementer in chief of the Integrated Resource Plan, has been a vocal supporter of the formerly dominant (but now increasingly less popular) coal, gas and nuclear sectors. Most recently, however, he has tried to reassure the solar and wind sectors that, despite perceptions to the contrary, he also supports renewable energy.

South Africa cannot solve a pressing energy crisis while senior government figures seem to openly disagree on the way forward. The message of joint commitment to the implementation of the electricity plan is therefore to be welcomed. Confidence would be further cemented by concerted attempts to reclaim lagging roll-out timelines and immediate moves to update the energy plan.

In the 2021 State of the Nation Address the President said the procurement of the first and second sets of renewable energy developments would commence in February and August 2021 respectively. The first target was achieved, but the second was postponed twice, first to January 2022, and then, late March 2022.

For this year’s address Ramaphosa indicated that the call for applications to procure the now severely delayed storage allocation as well as 3000 MW of gas generating capacity would be made later this year. This is insufficient to catch up with the backlog of new power plants.

The omissions and the climate change loan

The President also steered clear of controversial energy developments.

He didn’t say anything about the completion of the massive Kusile coal plant, which together with its twin Medupi, has been bedevilled by massive delays, cost overruns and inexplicable breakdowns of the still new machinery.

He was also silent on the 1500 MW of new coal plants envisaged under the Integrated Resource Plan, which would normally be expected to be allocated to developers soon. This may be a deliberate effort to play down any ambitions the country may have on this front so that these do not jeopardise R131 billion foreign grants and loans expected in exchange for adopting a climate-friendly energy development path.

Also not mentioned were the controversial gas ship emergency power initiative and the refurbishing of the Koeberg nuclear plant.

Instead, he praised a Northern Cape green hydrogen generation initiative – a storage technology that is mostly envisaged to work in tandem with renewable energy generation – even though this programme is still in the relatively early planning stages.

Regulatory changes and the unbundling of Eskom

The President’s biggest successes in the last year have been in regulatory matters. He eased power production licensing requirements to make it much easier for entities to set up power plants of up to 100 MW. This eased a bottleneck that has led to many more mines, municipalities and other private entities taking steps to establish their own power generating capacity.

In his speech Ramaphosa highlighted that this capacity is projected to reach 4000 MW for mines and 1400 MW for municipalities. This is considerably higher than would have been envisaged as little as five years ago. This will go some way to bridging the electricity shortfall.

To convince the sceptical nation that the energy crisis was being dealt with the President needed something new. To do that, on the day of the address, government released for public comment a draft revised electricity bill. This includes several proposed reforms that would erode the monopoly of the national electricity utility, Eskom.

The draft bill further establishes the operational framework for new entities that would result from an unbundled Eskom, a process that is expected to reach completion this year.

Debates on the impact of this new bill and around potential modifications will be prominent in the months to come, and the outcome of this process will decisively shape the future of electricity developments in South Africa.

In particular, the bill will boost small scale private electricity production – also referred to as “embedded” generation – and outstrip its contribution projected in the current Integrated Resource Plan. Technological advances in electricity storage are also making it viable to use larger fractions of intermittent solar and wind power than previously anticipated.

This calls for a redetermination of South Africa’s optimal electricity mix through a new Integrated Resource Plan. The work towards this must start now.The Conversation

Hartmut Winkler, Professor of Physics, University of Johannesburg

This article is republished from The Conversation under a Creative Commons license. Read the original article.

COMMENTS   3

Sort by:
  • Oldest first
  • Newest first
  • Top voted

You must be signed in and an Insider Gold subscriber to comment.

SUBSCRIBE NOW SIGN IN

The Eskom (and SAA) playbook and the Dakota Indian Dead Horse Theory …

The tribal wisdom of the Dakota Indians, passed on from one generation to the next, says that when you discover that you are riding a dead horse, the best strategy is to dismount.

But in modern business, because heavy investment factors are taken into consideration, other strategies are often tried with dead horses, including the following:

1. Buying a stronger whip.
2. Changing riders.
3. Threatening the horse with termination. 
4. Appointing a committee to study the horse. 
5. Arranging to visit other sites to see how they ride dead horses. 
6. Lowering the standards so that dead horses can be included. 
7. Reclassifying the dead horse as “living-impaired”. .
8. Hiring outside contractors to ride the dead horse. .
9. Harnessing several dead horses together to increase speed.
10. Providing additional funding and/or training to increase the dead horse’s performance.
11. Doing a productivity study to see if lighter riders would improve the dead horse’s performance. 
12. Declaring that the dead horse carries lower overhead and therefore contributes more to the bottom line than some other horses.
13. Rewriting the expected performance requirements for all horses.
14. Promoting the dead horse to a supervisory position.

Sigh …

There are three pumped storage schemes already studied (Lima, Kabong and Ceres) and at least one is already through EIA and already has the lower dam in place.

They would add 4000MW capacity and about 30h of storage to the transmission network to use. Use = absorb renewable surpluses and discharge to avoid horrific and constrained diesel peakers and it can act as black start facility.

One rule : Ingula cost 2.5 times what it should through sheer incompetence and corruption. PS schemes must be EPC Turnkey projects.

Cost is high probably $7 billion but with levelised cost of storage of likely less than 50c/kWh a crucial tool for managing our energy mix. Even more so if we add 15 to 20 GW of renewables

Thanks for this; good options on the downstream portions of KZN’s major rivers as well but ANC, no action likely. Umgeni one was investigated maybe 30 years ago at least. Lesotho Highlands scheme (schlenter) was investigated from the mid 1950’s (as the Oxbow scheme). Just for interest.

End of comments.

LATEST CURRENCIES  

USD / ZAR
GBP / ZAR
EUR / ZAR
BTC / USD

Podcasts

Instrument Details  

You do not have any portfolios, please create one here.
You do not have an alert portfolio, please create one here.
INSIDER SUBSCRIPTION APP VIDEOS RADIO / LISTEN LIVE SHOP OFFERS WEBINARS NEWSLETTERS TRENDING

Follow us: